Electric Line Extension

Anaheim Public Utilities is extending underground electrical circuits to provide additional capacity to Central and South Anaheim for improved reliability. 

Active Line Extension Projects:



Katella Line Extensions: 

  • Extend multiple 12kV circuits (approximately 7,000 feet) along Katella Avenue from State College Blvd to Douglass Road to provide additional capacity to the Angel Stadium and OCVibe developments 
  • Estimated construction start and end dates: Summer 2022 – Summer 2023
  • Project ViewFinder - Project Tracker ID#4436

Southwest Substation Line Extensions: 


  • Re-configure, relocate and extend new and existing 12kV circuits as part of the Southwest Substation upgrade located north of Energy Field Park along Ninth Street
  • Estimated construction start and end dates: Spring 2022 – Winter 2022
  • Project ViewFinder - Project Tracker ID#4448

Wanda Line Extensions Phase II: 


  • Extend Wanda 12kV circuit along Ball Rd from Claudina St to State College Blvd provide additional capacity to the area
  • Estimated construction start and end dates: Winter 2021 - Fall 2022
  • Project ViewFinder - Project Tracker ID#2400

Contact Us

  1. Electrical Engineering 


    Call: 714-765-5156 or Email
    ACH/Hearing Impaired 
    TDD: 714-765-5125

    Office:


    Mon. - Fri.: 8 a.m. - 5 p.m.
    Anaheim West Tower
    201 S. Anaheim Blvd. 
    Anaheim, CA 92805 Map

    Utilities Directory
Project Contact:

Manuel Soto 
714.765.4271